11 hot news about offshore wind power (2021.11.06-11.12)

2021/11/12 Source:ChinaOffshoreWind

1. National Energy Administration: As of the end of September, the total installed capacity of offshore wind power nationwide was 13.19 million kilowatts!

On November 8, 2021, the National Energy Administration will hold an online press conference for the fourth quarter to announce the energy situation and grid-connected operation of renewable energy in the first three quarters. Among them, from January to September 2021, 1643 new grid-connected wind power installations nationwide 10,000 kilowatts, of which 12.61 million kilowatts were newly installed for onshore wind power and 3.82 million kilowatts were newly installed for offshore wind power. In terms of the distribution of new installed capacity, the central and eastern and southern regions accounted for about 60%, and the "Three North" regions accounted for 40%. The layout of wind power development has been further optimized. By the end of September 2021, the cumulative installed capacity of wind power nationwide was 297 million kilowatts, of which 284 million kilowatts of onshore wind power and 13.19 million kilowatts of offshore wind power.

Source: National Energy Administration


2. The first batch of units of my country's first flexible DC offshore wind power project were officially connected to the grid for power generation

On November 8, the first unit of the Three Gorges Group Jiangsu Rudong Offshore Wind Power Project (referred to as the Three Gorges Rudong Project) officially sent power to the Jiangsu Power Grid, marking the successful connection of the first batch of units of my country’s first flexible DC offshore wind power project to the grid.

The Rudong Three Gorges Project is located in the Huangshayang waters of Rudong County, Jiangsu Province. It is the first offshore wind power project in Asia that uses flexible DC transmission technology. The generated energy is transmitted to the grid through a flexible DC transmission project (referred to as Rudong Flexible Direct Project). The project is mainly composed of two sea booster stations, an offshore converter station, a DC submarine cable, and an onshore converter station.

The Rudong Three Gorges project will be put into operation in December this year. By then, the annual on-grid power will reach 2.4 billion kWh, which can meet the annual power consumption of about 1 million households. Compared with coal-fired power plants of the same scale, it can save standards every year. Burning approximately 740,000 tons of coal and reducing carbon dioxide emissions of approximately 1.83 million tons will add kinetic energy to optimize the local energy structure and ensure power supply this winter and next spring, effectively helping to achieve the goal of "carbon peak and carbon neutrality".

Source: China Three Gorges Energy


3. The wind power installation platform "Guardian" Nanhai started construction, and the lifting of offshore wind turbines added another weapon

On November 7, Energy China Southern Construction Investment Guangdong Thermal Power used the "guard" installation platform introduced by the nation's first transformation plan to successfully complete the first show of wind turbine hoisting at Huadian Yangjiang Qingzhou Three 500MW Offshore Wind Power Project.

The "Guard" installation platform is an offshore construction and installation platform modified from the "H194" drilling platform. It uses the advantages of the drilling platform's own deep-sea operation characteristics to meet the positioning operations in deeper seas; the "Guard" installation platform is equipped with "DP1" dynamic positioning System, 650-ton full-rotation offshore crane and double side-side auxiliary crane, with strong hoisting operability, with nearly 129-meter-long pile legs, large pile shoe area, low pile shoe unit preload load, and better performance in mud entry For most wind power installation platforms, the pile legs are used for water depth and the range of lifting height is larger; the "guard" installation platform can serve for deeper and higher offshore wind turbine hoisting construction, which can meet the water depth of more than 50 meters and offshore wind turbines of more than 8.0 MW Install.

The successful hoisting of the first fan of the "Guide" installation platform (No. 17) marks the successful practice of the fan hoisting scheme of the "Guangdong Thermal Power" retrofit platform, and provides a useful reference experience for the hoisting construction of the wind power installation platform in the deep water area. It also provides a solid guarantee for the efficient installation of the subsequent fans of the project.

Source: Energy China Guangdong Thermal Power


4. Successful installation of the first 7MW offshore wind turbine in the waters of southern Zhejiang

On November 4th, with the perfect docking of the 22# fan impeller and generator at an altitude of 115 meters, it marked the successful installation of the first impeller of the Huadian Yuhuan No. 1 offshore wind power project undertaken by the company, and it was also a deep silt sea area in southern Zhejiang. The installation of the first impeller completed by a wind turbine installation ship not only opened the curtain on the impeller installation of Huadian Yuhuan No. 1 Project, but also provided useful experience for future large-scale and affordable offshore wind power construction in the deep silt sea area of southern Zhejiang.

At present, the company has organized 3 fan installation work faces for fan hoisting. According to the requirements of the project schedule, 1-2 fan installation work faces will be organized in the future. At that time, a hoisting competition situation will be formed, which is the full capacity of the project. Grid-connection builds a solid guarantee.

Source: Huadian Heavy Industry Co., Ltd.


5. The steel pipe pile sinking construction of Shantou's first offshore wind power project was completed

On November 10, the last single pile of Datang Nan'ao Lemen I Offshore Wind Farm Project Bid Section 2 contracted by the New Energy Branch of China Railway Construction Port and Shipping Administration was successfully completed, marking the completion of the steel pipe pile of the wind farm. The pile sinking tasks are all completed.

Datang Nan'ao Lemen I Offshore Wind Farm Project Tender Section 2 construction tasks mainly include 18-station wind turbine foundation construction, tower tube manufacturing, wind turbine installation, and the actual construction of 19 single piles through the coordination of the owner. Among them, the largest single pile of the wind farm weighs about 1,570 tons, and the pile length is about 101 meters. Since the start of the construction of steel pipe piles, the project department has overcome various unfavorable factors. It took 72 days to complete the construction of all 19 steel pipe piles.

It is reported that the total installed capacity of Datang Nanao Lemen I offshore wind farm is 245 MW. After the construction is completed, the annual power generation is expected to be 751 million kWh and the output value is 565 million yuan. It can save 240,000 tons of standard coal and reduce carbon dioxide emissions 45 10,000 tons, will effectively promote the large-scale development of offshore wind power generation in Shantou.

Source: Longchuanfeng Power Grid


6. Fuzhou Fuqing Haitan Strait Offshore Wind Power Project will connect full capacity to the grid for power generation

On the blue sea on the northeast side of the Longgao Peninsula in Fuqing, the 46 wind turbines planned for the Haitan Strait Offshore Wind Power Project have been hoisted, and it is planned to achieve full-capacity grid-connected power generation in mid-November.

The Haitan Strait 300MW offshore wind power project is a key project of Fujian Province and the first offshore wind power project of China Huadian Group Co., Ltd. The main project started in November 2019, and the first two wind turbines were connected to the grid in December 2020.

As of the end of last year, Fujian's offshore wind power has been connected to the grid with a total of 760,000 kilowatts, ranking third in the country.

Source: Fuzhou Daily


7. Release of 60M new offshore wind power operation and maintenance mother ship

Polaris Wind Power Network learned that on November 5, Fujian Shipbuilding Heavy Industry Co., Ltd. ("Fujian Shipbuilding") held a launch conference for a new type of 60M offshore wind power operation and maintenance mother ship, and released the first domestic offshore wind power that meets the requirements of the China Maritime Safety Administration. Field operation and maintenance mother ship.

It is understood that the new ship type is a brand-new ship type developed by Fujian Shipping Administration. The ship type design approval has been completed by the Fuzhou Branch of China Classification Society, and it complies with the relevant regulations and standards of the China Classification Society and the national competent authority. The ship has a total length of about 59.6 meters, a molded width of 16.4 meters, a molded depth of 6.2 meters, a displacement of 3483 tons, a design speed of no less than 12 knots, and can provide accommodation for more than 60 people. Offshore wind power operation and maintenance personnel create a comfortable and comfortable work and life platform. Compared with similar European ship types, it has more advantages in terms of performance indicators such as occupancy, deck area, working and storage rooms, self-sustaining capacity, positioning ability, fuel consumption, deadweight tonnage, safety, and accessibility.

Source: Polaris Wind Power Network


8. Yudean plans to invest 17.1 billion yuan to construct Yudean Yangjiang Qingzhou I and Qingzhou 21 million kilowatt offshore wind power projects

On November 9, Guangdong Electric Power Development Co., Ltd. issued an announcement on the investment and construction of Yudean’s Yangjiang Qingzhou 1 and Qingzhou 21 million kilowatt offshore wind power projects. The Proposal on Investing in the Construction of Yudean Yangjiang Qingzhou One (400,000 kW) Offshore Wind Power Project" and the "Proposal on Investing in the Construction of Yudean Yangjiang Qingzhou Two (600,000 kW) Offshore Wind Power Project", in order to accelerate the company’s large-scale development of new energy power generation projects To increase the proportion of clean energy installed capacity and optimize the power supply structure, the company’s board of directors agreed to the company’s wholly-owned subsidiary Guangdong Wind Power Co., Ltd. Dianyangjiang Qingzhou No. 2 Offshore Wind Farm Project has a total construction scale of 1 million kilowatts and a total dynamic investment of 17.107 billion yuan.

Source: Guangdong Electric Power Development Co., Ltd.


9. 3.6GW, impeller diameter of 236 meters! 14MW offshore wind turbine wins another big order

Recently, Siemens Gamesa and Vattenfall reached an agreement on the designated preferred supplier for the Norfolk offshore wind power project in the UK. The total installed capacity of the project is 3.6GW, 47-72 kilometers away from the coast, and the newly upgraded SG 14-236 DD offshore wind turbine will be installed. The project is divided into two sites, Norfolk Vanguard and Norfolk Boreas, each with 1.8GW.

The upgraded SG 14-236 DD offshore wind turbine impeller has a diameter of 236 meters, the sweeping area has increased to 43,500 square meters, and the power can be increased to 15 MW, which is 30% higher than the power generation of SG 11.0-200 DD. The project plans to install prototypes in 2022 and realize commercialization in 2024.

According to previous reports, in 2020, Siemens Gamesa released the SG14.0-222 DD model based on the 14MW platform "1X" for the first time; in September of this year, Siemens Gamesa’s SG14.0-222 DD prototype started at the test center in Østerild, Denmark The installation is scheduled to be put into operation before the end of the year. This milestone will greatly accelerate the installation of the SG 14-236 DD prototype in 2022.

Source: Polaris Wind Power Network


10. The total investment exceeds 10 billion U.S. dollars! Ørsted deploys 3.9GW offshore wind farm in Vietnam

The Danish energy giant Ørsted plans to invest USD 13.6 billion (EUR 11.75 billion) to deploy a 3.9 GW offshore wind farm project in Vietnamese waters. This huge project is expected to be implemented in three phases, with a total investment of between US$11.9 billion and US$13.6 billion.

Ørsted plans to deploy wind farms 14 kilometers (8.7 miles) southwest of Bach Long Vy Island in the Beibu Gulf and 36 kilometers northwest of Long Chau Islands. The height of the hub of the wind turbine is between 150m and 200m. If completed, the wind power complex will be able to generate approximately 13.7 million megawatt-hours of electricity each year.

Source: Offshore Wind Focus


11. The world's first tension leg based floating wind power project will land in the UK!

A few days ago, SBM Offshore, a floating technology company headquartered in the Netherlands, and Cierco Wind Energy, a floating technology company headquartered in California, USA, formed a joint venture company Floventis Energy, which will jointly build two floating wind power demonstration projects in the Celtic Sea, Scotland. Participate in 2GW floating wind power projects worldwide in the next 10 years.

Source: European offshore wind power