Pingtan Strait Offshore Wind Power Project completed the first wind turbine hoisting

2021/09/24 Source:ChinaOffshoreWind

At the general debate of the 76th UN General Assembly, President Xi Jinping delivered an important speech: "China will strive to achieve carbon peaks by 2030 and carbon neutrality by 2060. This requires hard work, but we will do our best. ."


Facing the national proposition of "carbon peaks and carbon neutrality", Yongfu shares always take "making electricity cleaner and smarter" as its mission, continue to advance on the waves, and continuously promote the high-quality development of offshore wind power!


At 23:30 on September 18th, with the smooth decoupling of the third blade clamp of the No. 4 wind turbine, the installation of the first wind turbine for the decentralized offshore wind power project of the Pingtan Strait Road-Rail Dual-purpose Bridge Lighting Project undertaken by Yongfu Co., Ltd. was successfully hoisted.


The decentralized offshore wind power project of the lighting project of the Pingtan Strait Road-Rail Bridge is the first offshore wind power project in Fujian Province that adopts the EPC construction mode of general contracting, and is also the first decentralized offshore wind power project in China.


The project site is located on the northeast side of Xiaolian Island in the Taiwan Strait, one of the world's three major wind vents. It has the characteristics of strong wind, high waves, deep water, rapid currents, high construction difficulty, and short window period. It has many technical challenges and construction risks. During the hoisting of the first wind turbine, it also experienced multiple tests of the prevention and control of the No. 13 and No. 14 double typhoons and the local new crown epidemic.


The project department has successively overcome difficulties such as the complex terrain of the construction sea area, the windy airport site and the high wind and high tide, and the tension of the sea rushing to load the tide ship. Completed the installation of the first wind turbine and accumulated experience for the subsequent hoisting of the project.


Yongfu Co., Ltd. will continue to maintain a high morale, coordinate the promotion of project construction, make full preparations for the smooth grid connection of the project, and contribute to the construction of a clean, low-carbon, safe and efficient modern energy system, and to promote the improvement of the energy structure of Fujian Province and the transformation and upgrading of green energy.